The Grand Pont in Lausanne, designed by the visionary engineer Adrien Pichard, spans the Flon Valley from east to west. It is a 170-meter-long multi-span, rubble masonry arch bridge comprising two superimposed arcades, that was commissioned in 1844. The lower level was buried when the Flon Valley was backfilled in 1873. The upper level, which is comprised of 19 arches, is still visible and in use. The deck had already been widened once in 1891 using a metal frame in order to allow trams to cross over it, and then again in 1933 using concrete free cantilever structures.

In 2011, a plan to widen the deck was drawn up in connection with changes to the tram system, but this was blocked as a result of objections and never came to fruition. After several years in limbo, an inspection and investigation campaign was undertaken in 2020 which revealed deterioration of the concrete free cantilever structures (corrosion of the framework and cracks in the concrete). In addition, it was found that the entire slab was insufficiently waterproof and that the bridge was therefore full of water, which was dissolving the mortar joints and causing pieces of rubble to come away. Static inspections of the free cantilevers and the railings also found evidence of major structural non-conformities.

Consequently, a reconstruction plan was drawn up for the Grand Pont that involved replacing the concrete free cantilever structures with a new slab made of pre-stressed concrete. The slab is designed to ‘float’ above and protect the masonry arches without impairing the view of them or interrupting the flow of the bridge. The slab is therefore completely free of struts, is covered in a UHPFRC mineral waterproof coating and finished off with slim UHPFRC side edges.

Since the structure is listed as a historical monument, the project was carried out under the guidance of the Heritage Departments of the City of Lausanne and the Canton of Vaud. These consultations resulted in the existing railings, which date back to 1891, being partially retained. This involved disassembling all of the railing panels, sanding them down, reinforcing them, and returning them to their original position. The uprights of the railings were recast. Organically shaped lighting columns, each with two arms culminating in a bowl, are mounted atop the railing uprights anchored to the piers in order to lend the Grand Pont its own unique style of illumination.

  • Bauherr

    Amt für Strassen und Mobilität – Stadt Lausanne
    TL – Öffentlicher Verkehr der Region Lausanne

  • Bauingenieure

    Bauingenieurgruppe IG Grand-Pont:
    INGPHI SA, Lausanne (Planung und öBL)
    Bächtold & Moor AG, Bern (Kontrolle)

  • Ausgeführte Leistungen

    Detaillierte Inspektion
    Planung und Überwachung der Untersuchungen
    Vorprojekt
    Bauprojekt
    Ausschreibung
    Ausführungsprojekt
    Bauleitung

  • Technische Daten

    Länge 170 m
    Breite 15,30 m
    Lehnenkonstruktion 62 m
    Mauern 30 m

  • Baujahr

    2011 -2022

Veröffentlichungen

  • Publication Grand-Pont – Revue Tracés – Construire – Décembre 2022

    Article “Remise en état du Grand-Pont à Lausanne” dans la revue Tracés – Construire. Par Philippe Menétrey, Guillaume Fargier et Sophie Tschumy.

Projektteam

  • Guillaume Fargier-INGPHI

    Guillaume

    Fargier

    Projektleiter - Bauingenieur

  • hugo-crespo-equipe-ingphi

    Hugo

    Crespo

    Techniker Arbeitsplanung

  • jonathan-krebs-equipe-ingphi

    Jonathan

    Krebs

    Mitglied der Geschäftsleitung - Projektleiter - Bauingenieur

  • Kushtrim Bajrami

    Kushtrim

    Bajrami

    Zeichner

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Direktor - Projektleiter - Bauingenieur

  • Sophie Tschumy-INGPHI

    Sophie

    Tschumy

    Bauingenieurin

  • Tamás

    Szabó

    Zeichner

estacade-epesses-ingphiLehnenkonstruktion von Epesses
modelisation-hotel-des-horlogers-ingphiHotel des Horlogers