The concrete plant has been set up on the construction site. Important lifting equipment was required to lift the various elements and install them near the excavation, which is over 10 meters deep. In particular, a 300-tonne mobile crane was installed at the top of the bored pile diaphragm wall, following a procedure specially developed for this site. Prior to the operation, the wall was checked using ZSoil to ensure that it could support the 180 tonne load from the outrigger plates of the crane.