At the Paudèze bridges, the end is near…

The concreting works for the slab and the parapets on the Lake-side bridge are now over.

On the Mountain-side bridge, the execution of the parapets is ongoing, with 80-m long concreting steps. The rehabilitation of the upper face of the slab has started and the waterproofing layer. Wearing course will be placed during the month of September.

Under the bridges, the tiebacks at the head of the retaining shafts were placed and the drainage ditches where executed on the hillsides. The execution of the wellheads can now start.