The aqueduct, on the border between the cities of Montreux and Veytaux, allows the Veraye river to flow over the Lausanne – Brigue railway line, as well as the crossing of footpaths that line the river’s banks. The masonry arch structure was built in 1898 and has been damaged by seepage through many masonry joints. Also, the height under the arch is not sufficient for the new clearance desired by the railway company (CFF).

The project thus consists in building a new aqueduct made of reinforced concrete above the previously existing arch.

The construction of the aqueduct above the existing arch required raising the river profile. This correction affected the river over lengths of 29.5 m upstream and 16 m downstream from the aqueduct. The bed of the river, which can become a torrent, was covered with granite paving stones, with some protruding to slow the water flow.

The structure of the aqueduct is a self-supporting trough of reinforced concrete with a span of 21.2 m supported at the ends by springers connected to bored piles. These foundations transmit the vertical loads deep into the ground and ensure the stability of the banking during the demolition of the arch, by taking up the horizontal thrust of the soil.

The footpaths, 2.15 m wide, are located either side of the aqueduct. They are formed by a reinforced concrete deep slab and parapets that are connected to the trough. The aqueduct and the footpaths thus form a single monolithic unit; as if they were sculpted from a single block.

This project, at the limit between two cities and at the crossing of a river and a railway track required the correction of numerous industrial supply networks. These networks were all integrated into the structure, under the footpaths.

The site design is completed with a new reinforced concrete footbridge over the Veraye river and a footpath providing access to the sides of Lake Geneva.

  • Owner

    SBB AG, Project Management

  • Civil and geotechnical engineer

    INGPHI SA, Lausanne

  • Provided Services

    Preliminary Design
    Design
    Tender
    Detailed Design
    Supervision of Construction Works

  • Technical Characteristics

    Length: 21.20 m
    Width: 15.85 m

  • Construction Period

    2006 - 2017

  • Construction Company

    JPF Construction SA, Bulle

News

No news linked to this project.

Project Team

  • Claude Broquet-INGPHI

    Claude

    Broquet

    Manager - Project Manager - Civil Engineer

  • Jonathan Duruz-INGPHI

    Jonathan

    Duruz

    Draftsman

  • ninh-tran-equipe-ingphi

    Ninh

    Tran

    Associate - Internship supervisor - BIM Manager & Draftsman and builder

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Manager - Project Manager - Civil Engineer