At the start of August, the placement of the UHPFRC struts and the concreting of the cantilevers on the upstream sides of both bridges was completed. The construction of the parapets is ongoing and will be completed at the end of August. The new features of the bridges are slowly revealed.

The damaged cover concrete of the box-girders of the lake side bridge is being removed with high pressure water jets and rehabilitated.

Inside the box-girders, the steel deflector plates for the external additional prestressing cables are assembled. They will then be sealed to the concrete. The placement of the prestressing cable is ongoing.