… we work day and night!

Rehabilitation of the concrete and rebars of the span over highway N12 is done overnight. These night works are needed to ensure the security of the highway users as well as the workers.

During the day, concreting works of phase 2.3 are ongoing on the Bern side of the bridge, with the reinforcement of the cantilever and the replacement of the curb. Therefore, beginning of September, waterproofing and pavement works will start to complete this work phase. Only work phase 2.4 and the construction of the sidewalk will then remain.