After Three years, works are almost done!

During the month of September, the waterproofing and wearing courses were placed on the last third of the roadway of each bridge. The new noise barrier of the lake-side bridge was also installed. The various equipment was mounted.

Works on the roadway are almost done. The mountain-side bridge was completely reopened to traffic on October 12. Some finish works are ongoing on the lake-side bridge until the end of October.

Under the bridges, works will continue until the end of the year. It includes the seismic reinforcement of piers 04 and 104, the landscaping around the retaining shafts, the prestressing of the additional external cables and the removal of the scaffolds.