• Design

    Design

  • Design

    Project

  • Design

    Execution

  • Design

    Construction

The Auberge underpass is a vaulted masonry structure that was built in 1860. The vault is framed by large lateral piers to support the load of the arch. In addition, these piers ensure the transition between the vertical tympana of the vault and the batter of the long retaining walls.

The structure had several signs of deterioration, including water infiltration, deteriorating masonry joints, a non-compliant curb and insufficient width for SBB railway standards.

The project involved installing a new reinforced concrete deck on the masonry vault. The geometry of the section takes into account a future railway line distance of 3.80 m (12 ft.) on center. It also incorporates a sound barrier on the upstream side and curb lanes to accommodate the curve of the tracks on the rectilinear structure.

Due to the thickness of the new deck, an elevation (along the railway length) of 70 cm (28 in.) above the underpass is necessary to ensure a minimum ballast thickness under the track ties. As a result, the profile was adapted under the terrace of the Grand Hotel to satisfy clearance requirements and lower a section of the quays of the Territet station, covering 573 m (1,880 ft.).

The masonry of the vault, the large piles that frame it as well as the retaining walls were refurbished.

The new reinforced concrete deck was made on a temporary support placed parallel to the underpass on the lake side. The pre-ballasted deck was then shifted onto the masonry structure to its final position with railway traffic completely interrupted.

To shift the deck, four lanes were equipped with an independent traction cylinder. The concrete deck was lowered onto the masonry vault after it was shifted. The interface between the old bridge and the new structure was injected with mortar to ensure uniform load transfer.

The deck trough is therefore a monolithic structure equipped with a continuous waterproofing layer.

  • Owner

    SBB AG, Project Management

  • Civil and geotechnical engineer

    INGPHI SA, Lausanne

  • Provided Services

    Preliminary Design
    Design
    Tendering
    Detailed Design
    Supervision of Construction Works

  • Technical Characteristics

    Length: 29 m
    Width: 12 m

  • Period

    2006 - 2017

  • Construction Company

    JPF Construction SA, Bulle

Project Team

  • Claude Broquet-INGPHI

    Claude

    Broquet

    Manager - Project Manager - Civil Engineer

  • Jonathan Duruz-INGPHI

    Jonathan

    Duruz

    Draftsman

  • ninh-tran-equipe-ingphi

    Ninh

    Tran

    Associate - Internship supervisor - BIM Manager & Draftsman and builder

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Manager - Project Manager - Civil Engineer

logements-et-equipements-sociaux-a-perly-ingphiSocial Housing and Infrastructure
modelisation-manufacture-horlogere-glovelier-ingphiTimepiece Manufacturing Facility in Glovelier