Timelapse of the erection of the wooden modules

During the month of July, the entire framework of the training hall was erected. The modules, which were prefabricated in the workshop, were put in place by means of the construction crane within three weeks.

The 24 frames consisting of 60cm x 22cm columns and 230cm x 22cm crossbeams were delivered by special transport and put in place without continuity assembly.

Framing panels – providing bracing – are placed between the columns and the CLT roof is screwed to the roof beams.