• Inspection

    Inspection

  • Inspection

    Project

  • Inspection

    Execution

  • Construction

The bridges over the Flon were designed in 1964 by Sarrasin consultancy firm, a Swiss pioneer in reinforced concrete bridges. They are illustrative of the technique used for building reinforced concrete bridges that minimises the use of materials.

The mountain side bridge over the Flon is in poor condition. The degradation of the half-joints is particularly concerning. This poses a risk for the structural integrity of the bridge.

The aim of the repair project is to concrete every half-joint thus removing any risk associated with keeping them (brittle failure, fall of deck in case of seismic activity & progressive degradation). The joints will be concreted using temporary steel structures placed under the deck, linking both sides of the joints. The joints are then demolished, thus removing all chloride contaminated concrete.

The abutments are designed to include manholes, with expansion joints and sliding bearings that are easily accessible for any maintenance work.
The deck slab is reinforced by removing an old concrete sidewalk, milling the cover concrete and adding a micro-concrete layer on the whole surface. The arches, piers and stringer beams are reinforced to maintain the integrity of the bridge. These reinforcements are made by wrapping the different concrete parts with carbon sheets or lamellas (CFRP).

The noise barriers laterally attached to the deck are removed, treated for corrosion and refitted. Only the acrylic panels are changed. The re-use of the steel profiles allows compliance with sustainable development criteria.

The construction project allows continuous traffic on the bridge during the works with only three work phases during which traffic lanes are modified.

The rehabilitation project of the Mountain side bridge over the Flon is a rational and coherent project allowing, by the suppression of the half-joints, to raise the safety and robustness of the bridge while extending its service life.

  • Owner

    Swiss Federal Road Office

  • Civil Engineer

    INGPHI SA, Lausanne

  • Provided Services

    Final Design
    Tendering
    Detailed Design
    Technical Supervision of Construction Works

  • Technical Characteristics

    Length: 430 m
    Arch Span: 123 m

  • Period

    2016 - 2018

  • Construction Company

    Walo Bertschinger SA, Romandie

Project Team

  • Claude Broquet-INGPHI

    Claude

    Broquet

    Manager - Project Manager - Civil Engineer

  • Guillaume Fargier-INGPHI

    Guillaume

    Fargier

    Project Manager - Civil Engineer

  • Jonathan Duruz-INGPHI

    Jonathan

    Duruz

    Draftsman

  • Lionel Moreillon

    Lionel

    Moreillon

    Associate - Project Manager - Construction works supervision and management - Civil Engineer

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Manager - Project Manager - Civil Engineer

  • Rui Costa-INGPHI

    Rui

    Costa

    Draftsman - Internship supervisor

  • Sarah Derian-INGPHI

    Sarah

    Derian

    Project Manager - Civil Engineer

Qatar National Museum
Securing and Repairing the Lavapesson Bridge