End of concreting

Work on the training hall in Magglingen is continuing. The slab of the triple sports hall is nearing completion: the precast slabs have been laid, the prestressing cables for the 22 m spanning beams to cross the wrestling hall have been tensioned, and the concreting of the last stage is scheduled for this week.

The concrete work will be completed in one month and the assembly of the wooden structure is scheduled for this summer.