The Chandelar bridge on the RC 773 road between the municipalities of Pully and Belmont was built in 1967.It is slightly curved and has three spans measuring 24.2 m (79 ft.), 32.6 m (107 ft.) and 24.2 m (79 ft.) for a total length of 81 m (266 ft.). It is a floating bridge that is rigidly supported on its two piers and on the abutment bearings. The cross section of the central rib contains five cylinders of expanded polystyrene to lighten the section.

The bridge deck was partially deteriorated, the prefabricated curbs were damaged and let water seep under the deck, the surface of the sidewalks was never waterproofed, the surface course was worn and the joints were damaged and not watertight.

The structure therefore needed complete stabilization. Existing curbs and sidewalks were reprofiled with a layer of UHPFRC, providing a dual function as a waterproofing and wear layer. The waterproofing membrane, the coating and the expansion joints were replaced.

The bridge was also reinforced at the structural level, as the shear reinforcement near the piers was insufficient to support current traffic loads. A reinforcement project was developed to maintain the look of the existing bridge. The expanded polystyrene cylinders that had been installed during construction were replaced by fiber reinforced concrete (FRC) for 3 m (10 ft.) on either side of the piers in order to create large “shear pins.” Inclined prestressed rebars were also added throughout the transverse beams.

This project perfectly illustrates how innovation contributes at the material level. By using just the right amount of fiber reinforced concrete, it was possible to strengthen the Chandelar bridge without modifying the look.

  • Owner

    Road Department of Canton of Vaud

  • Civil Engineer

    INGPHI SA, Lausanne

  • Provided Services

    Design
    Tendering
    Detailed Design
    Supervision of Construction Works

  • Technical Characteristics

    Length: 81 m
    Width: 10.50 m
    HPFRC 40 m3
    UHPFRC 20 m3

  • Period

    2013 - 2014

  • Construction Company

    Frutiger SA Vaud, Savigny

News

No news linked to this project.

Project Team

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Manager - Project Manager - Civil Engineer

logements-bethanie-lausanne-ingphi-realisationBéthanie Apartments
estacades-flon-passage-inferieur-ingphi-realisationCorniche Structures and Underpass on the Route de Glion