Canton of Vaud is planning the construction of a building that will house the Musée de l’Élysée (Cantonal Museum of Photography) and the mudac (Museum of Contemporary Design and Applied Arts) on the Plateforme 10 site in Lausanne. The new building will take form behind the Cantonal Museum of Fine Arts in the area where the former CFF locomotive sheds of the Lausanne train station were located.

The structure is composed of two concrete masses that come into in direct contact, brush up against each other and then open up through a geometric wave. A space floats between the two forms, separating the L’Élysée on the ground level from the mudac in the vault. Both museums and this space create prismatic volume, the different units detached by a peripheral hollow. By absorbing the limits of the ground, these units open up space around the museum to reveal light and crystalize the unity of the prism into which it breathes life.

Nearly 70 000 m3 of earth was excavated to prepare the site for its new occupant. Excavation support walls were constructed using soil-nail walls with a maximum height of 7 m, concrete soldier pile walls with a maximum height of 13 m and 23 m secant pile walls. Nearly 260 piles were drilled into till and molasse, and 150 bearing piles, reaching from 12 to 16 m into the ground, complete the structure to ensure that the entire building is supported on healthy molasse.

The main building—enveloping both museums—is composed of an underground level sealed with reinforced concrete that forms the rafters, walls and slabs in one monolithic piece. Given the invaluable nature of the artwork presented and stored there, the space will be fully watertight and a peripheral drainage system is to be installed. The gap between the two concrete masses holds the ground floor of the main building. This space, free of any walls, includes reception areas, the bookstore and the cafeteria. It also serves as a zone for circulation between the two museums as well as between the museums and the administrative spaces located in the building’s perimeter. The expansive slab that forms the vault of the gap is faceted with white concrete and hangs from structural steelwork comprised of trellises of variable geometry. This steel framework rests entirely on the building’s three cores, conjuring the illusion of the upper mass floating above the empty space. The structural framework holds up the upper level, which is supported by surrounding walls that both stabilize the entire unit and ensure the transfer of force to the cores. The sawtooth roof structure is also constructed of metal and acts as a tie rod between the walls. Single-pour, white concrete walls form the museum’s facades and hang suspended from interior bearing walls.

  • Owner

    Direction générale des immeubles et du patrimoine, Canton of Vaud

  • Architects

    Aires Mateus e Associados, Lisbon (winning bid)
    Iten+Brechbühl SA, Lausanne (local architect)

  • Civil engineer

    Afaconsult, Porto (winning bid)
    INGPHI, Lausanne (local engineer)

  • Provided services

    Preliminary design
    Design
    Tendering
    Detailed design
    Technical supervision of construction work

  • Technical characteristics

    Concrete soldier pile walls
    Secant pile walls
    Soil-nail walls
    Exposed concrete
    Structural steelwork
    Large cantilevers
    Complex geometry

  • Period

    2018 - 2021

  • Construction companies

    Orllati SA, Bioley-Orjulaz
    Marti Construction SA, Lausanne

Project Team

  • antony-samuelian

    Antony

    Samuelian

    Draftsman

  • hugo-crespo-equipe-ingphi

    Hugo

    Crespo

    Work Planning Technician

  • jonathan-krebs-equipe-ingphi

    Jonathan

    Krebs

    Associate - Project Manager - Civil Engineer

  • Katia Gomes-INGPHI

    Katia

    Gomes

    Project Manager - Civil Engineer - Quality Manager

  • Kushtrim Bajrami

    Kushtrim

    Bajrami

    Draftsman

  • Luca

    Moll

    Draftsman

  • ninh-tran-equipe-ingphi

    Ninh

    Tran

    Associate - Internship supervisor - BIM Manager & Draftsman and builder

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Manager - Project Manager - Civil Engineer

  • Rui Costa-INGPHI

    Rui

    Costa

    Draftsman - Internship supervisor

  • samuel-rochat

    Samuel

    Rochat

    Project Manager - Civil Engineer

  • Sarah Derian-INGPHI

    Sarah

    Derian

    Project Manager - Civil Engineer

  • Tamás

    Szabó

    Draftsman

  • Thanh Nhien Nguyen-INGPHI

    Thanh Nhien

    Nguyen

    Architect - BIM Coordinator

Sports Hall - Magglingen
New Apostolic Church Switzerland