• Inspection

    Inspection

  • Inspection

    Project

  • Inspection

    Execution

  • Inspection

    Completed

The bridges over the Paudèze river, located in the cities of Pully and Bemont, allow motorway N09 to cross the valley formed by the river with the same name. The two structures, to traffic in 1974, were built using the balanced cantilever method. Each bridge has five spans with a maximum length of 104 m.

Many inspections and assessments showed the bad sates of the bridges. The decks have significant mid-span deflections and the box girders are heavily cracked. Important prestress losses were also measured. The deck slab cantilevers are in poor condition with spalled concrete and corroded steel reinforcement on all edges. Important levels of chloride contamination have been measured in the concrete of the abutments.

In addition, the strength of the deck is insufficient for static loading. Seismic action also creates unacceptable concentration of action effects in one pier.
Thus, the bridges must be completely rehabilitated and strengthened.

The deck slab is to be reinforced by supporting its cantilevers with struts, allowing to maintain existing steel reinforcement in the slab. The struts will be made of ultra-high-performance fiber reinforced concrete (UHPFRC) to minimise their weight. Concrete parapets are to be built on the cantilever edges. The increase in weight requires placing additional longitudinal prestressing cables and the reinforcement of girder webs with carbon fiber reinforced polymer strips. The damaged sections are to be cut out and repaired. The abutments are completely reconstructed. The waterproofing system, the overlay as well as all the service equipment will be completely replaced. Finally, the end piers are strengthened for seismic actions.

Around the foundations, the Paudèze valley has areas with active landslides. In these areas, the piers are built on foundation shafts stabilised with active anchoring and a drainage system. However, failure of some tiebacks has been observed; they are to be replaced. In addition, two retaining foundation shafts are to be constructed upstream from the piers located in the landslide area, to reduce horizontal pressures on the foundations. The observational method is used to ensure the monitoring of geotechnical interventions.

  • Owner

    Swiss Federal Road Office

  • Civil Engineer

    LIG-A pool
    Lombardi SA, Fribourg
    (leader)
    INGPHI SA, Lausanne
    (APR Ponts Paudèze)
    GVH SA, Saint-Blaise + Tramelan IJA + GGT SA, Delémont

  • Provided Services

    Inspection
    Preliminary Design
    Preliminary and Design Project Phases
    Tendering
    Detailed Design
    Technical Supervision of Construction Works

  • Technical Characteristics

    Length: 404 m and 422 m
    Maximum Span: 104 m

  • Period

    2012 - 2020

  • Construction Company

    (Paudèze Bridge Pool)
    Frutiger SA, Vaud
    Jean Weibel SA, Bern

  • Geotechnical

    Karakas & Français SA, Lausanne

Project Team

  • Hugo

    Crespo

    Work Planning Technician

  • Jonathan Duruz-INGPHI

    Jonathan

    Duruz

    Civil Engineering Draftsman

  • Kushtrim Bajrami

    Kushtrim

    Bajrami

    Civil Engineering Draftsman

  • Lionel Moreillon

    Lionel

    Moreillon

    Associate - Project Manager - Construction works supervision and management - Civil Engineer

  • Luca

    Moll

    Civil Engineering Draftsman

  • ninh-tran-equipe-ingphi

    Ninh

    Tran

    Associate - Internship supervisor - BIM Manager & Draftsman and builder

  • Philippe Menétrey-INGPHI

    Philippe

    Menétrey

    Manager - Project Manager - Civil Engineer

  • Shkendim Salihi

    Shkendim

    Salihi

    Civil Engineering Draftsman - Internship supervisor

  • Tamás

    Szabó

    Civil Engineering Draftsman

Securing and Repairing the Lavapesson Bridge
gares_cevaCEVA Station Superstructures